The Building

Since its original construction in 1985, the building has undergone several major infrastructure upgrades to meet the needs of demanding telecommunications tenants.

These upgrades include:

  • The addition of a new DWP sub-station containing four 5,000-amp transformers.                                                                                                     
  • Six 2,000-KVA generators along with a 50,000 gallon underground fuel storage tank.                                                                                                                          
  • Three 100-ton cooling towers as well as a new "dry-pipe" pre-action fire suppression system and redundant service feeds into the Building from two separate locations on the fiber loop.                                                                                    
  • Fully addressable Fire Life Safety system                                                             